Power pole and line upgrade works in Melton South

We’re carrying out essential works on the electricity network to help keep power safe and reliable for the Melton South and surrounding community, while also supporting growing demand in the area.

Project type:Network Project
Current stage:Underway
Project duration:May 2026 – August 2026
Powercor

Upgrade works will include:

  • Replacement of power poles and powerlines
  • Some minor underground works on High Street

To allow our crews to complete these works safely, road closures and traffic changes will occur on:

  • Ferris Road
  • Western Freeway
  • Melton Highway
  • High Street

 

When

Works will be carried out intermittently from Monday 25 May 2026 until mid‑August 2026.

 

Traffic impacts

Most works will take place during the day using lane closures and stop/slow traffic management. Local access to businesses will be maintained where possible.

Some works will occur overnight under full road closures.

We’ll use this webpage to keep the community up-to-date on road closures and traffic changes.

 

What to expect

  • Traffic management will guide vehicles, cyclists and pedestrians safely around work areas
  • Some power outages may occur (affected customers will be directly notified)
  • Increased noise and vehicle activity in the area
  • Some works may take longer or be rescheduled due to weather or other factors
  • Some works will be noisy

 

Road closures and traffic changes

Ferris Road southbound road closure

Intermittent, between 13 July and 28 July 2026

  • Night works: 8:00pm–5:00am

Ferris Road northbound partial lane closure 

Partial lane closure only, through traffic maintained

Intermittent, 25 May – mid‑August 2026

  • Night works: 8:00pm–5:00am

Ferris Road / Western Freeway exit – lane closure, no left hand turn on to Ferris Road

Intermittent, between 13 July and 28 July 2026

  • Night works: 8:00pm–5:00am

Ferris Road exit lane (city‑bound slowdown)

Traffic will be reduced to 40km/ph during the below timeframes on the Ferris Road city bound exit lane

Intermittent, 25 May – mid‑August 2026

  • Weekdays: 9:30am–3:00pm
  • Weekends: 7:00am–7:00pm
  • Night works: 8:00pm–5:00am